Case study · Industrial

Warehouse slab & joint rehabilitation — live distribution facility

1,400 lineal metres of failed joints rebuilt and 60+ spall repairs completed without losing a single day-shift operating hour.

CS-04 / SLAB PLAN Warehouse slab & joint rehabilitation — live distribution facility
Drag to compare pre-works condition against completed remediation.

Problem

A distribution centre’s slab joints were destroying themselves and the forklift fleet that ran over them: spalled arrises at contraction joints, failed joint filler, and impact damage compounding at ramp transitions. The operator could not stop day-shift operations.

Diagnosis

Slab survey mapped joint condition across the facility into repair classes, correlated with traffic routes. The failure driver was undersized joint filler and eroded sub-joint support on the primary forklift routes — meaning like-for-like repair would fail the same way. Repair specification moved to semi-rigid epoxy joint rebuild with steel-armoured edges at the highest-traffic crossings.

Method

Works executed entirely on night shifts in zoned closures agreed with the operations manager, each zone returned to traffic before 5am using high-early-strength materials. Joints saw-cut and rebuilt with semi-rigid filler; spalls repaired with rapid-set repair mortar; armoured joint systems installed at ramp transitions; line marking reinstated per zone.

Outcome

Zero lost operating hours across the six-week program. Joint condition data handed over as a maintenance baseline, with a two-year re-inspection scheduled.

Representative case study — illustrates our documentation structure and methodology. Project facts to be replaced with verified works and client permission at launch (build plan §8).